This comprehensive installation manual provides essential guidelines for integrating rack-mounted servers into data cabinets. It details professional procedures for mounting rail kits and positioning high-power IT equipment safely and correctly. The guide emphasizes critical best practices, including mandatory ventilation clearances, load management techniques, and electrical safety precautions (e.g., requiring multiple personnel for heavy lifts). Ideal for IT technicians and system administrators, this resource ensures the proper setup of servers to maintain optimal airflow and prevent overheating in any professional data center environment.

📄 Preview PAGE OF 2

Page 1 Text Content

Warnings! 请注意!

The rack, chassis or guide rails may cause scratches, please be careful. 机柜或者服务器机箱、导轨可能造成划伤!

When installing new servers into the rack in use, please be aware of electric shock. 在正在使用的机柜中安装新服务器时,请谨防触电!

● When installing 2U or bigger servers, at least 2 people are needed. 安装2U或更大的机型时,至少需要2个人。 ● During the installation process, please do not block the vents on the server, especially the vents on the front and rear of the server. 安装时请注意不要阻塞服务器上的通风孔,尤其是服务器前、后部的通风孔。 ● Please remove the protective film from the server surface before using. 请在使用之前将服务器外壳上的保护膜撕去。 ● Please leave 15cm minimum of clearance on the front and rear sides of the server for proper ventilation.

Rack-mounted Server

服务器的前、后部需至少留出15厘米空间,以便于系统散热。 ● Please install air baffles for the position without device installed, to make sure that the server can get enough air flow, and to avoid air turbulence in the server room. 没有安装设备的机柜位置,请始终安装挡风盲板,以确保服务器获得足够的气流,并避免机房气流

Installation Guide

紊乱。 ● Servers are high-power electrical appliances, and they should be installed into dedicated cabinets with vents or professional water-cooled cabinets, to prevent system failures caused by overheating.

服务器是高功耗电器,只能安装在带有通风孔的专用机柜,或者专业水冷机柜中,以免过热造成系 统失效。 ● If it needs to install more than one devices, please load from the bottom up, and load the heaviest items first.

● Please note the cabinet’s load-bearing capacity, power supply capacity and heat dissipation capacity, be sure not to install devices beyond the cabinet’s bearing capacity. 请注意机柜的承重、供电及散热能力,切勿安装超出机柜承载能力的设备。 V1.0 ● For the convenience of using the front and rear ports of the server and cabling, leave 70mm minimum of clearance between the front end of the server and the inner side of the cabinet’s front door, and leave 150mm minimum of clearance between the rear end of the server and the inner side of the cabinet’s rear door. 为了便于使用服务器前、后部的接口,并便于布线,服务器前部与机柜前门内侧之间至少留出70 毫米、后部与机柜后门内侧之间至少留出150毫米距离。

If the device is more than 15kg, at least 2 people are needed.

15kg 安装超过15千克的设备时,至少需要2个人!

If the device is more than 30kg, at least 3 people are needed.

If the device is more than 50kg, at least 4 people are needed.

Please keep this document for future reference. 请保留本文档,以便于日后查阅。

Page Summary Contents For Inspur i24-LC Server Rack Installation Guide V1.0

Page 1 Warnings! 请注意! The rack, chassis or guide rails may cause scratches, please be careful. 机柜或者服务器机箱、导轨可能造成划伤! When installing new servers into the rack in use, please be aware of electric shock. 在正在使用的机...
Page 2 Rack-mounted Server Installation Guide机架式服务器上架安装指南 V1.0 Identifying the Rail Kit Contents 注意:左导轨的内轨必须安装在机箱左侧壁上;右导轨的内轨必须安装在机 服务器上架所需部件 Rail Kit is assembled by inner rail, middle rail and outer rail. 导...

Manual Details

Brand Server
Pages 2
File Size 2.44 MB
Published June 05, 2026
14 views

Enter the captcha to get the download link:

captcha

Frequently Asked Questions

安装大型服务器时需要多少人手?

如果设备超过15kg,至少需要2人;超过30kg需要3人;超过50kg则需要4人。

正确安装服务器到机柜时应注意什么筒和散热问题?

服务器前、后部需至少留出15厘米空间进行充分通风,且要为未安装设备的空位安装挡风盲板。

使用之前是否需要处理服务器的保护膜?

是的,在使用存储服务器外壳上的任何保护膜之前,都需要将其撕除。

机柜在承载、电气和散热方面有什么限制吗?

必须注意机柜的承重能力、供电容量和散热能力,不可安装超出其承受能力的设备。

传输线缆布线时需要预留哪些最小间距?

服务器前部与机柜前门内侧应保留至少70mm;后部与机柜后门内侧应保留至少150mm的距离。